Agency Platform Release Goals
ADOA-ASET continuously works to identify potential security/maintenance needs and enhancement opportunities for the Agency Platform Distribution. These opportunities are considered by a subcommittee for implementation in upcoming releases.
Background and strategic fit
- Integrate core, security, contributed components, and theme enhancements in order to guarantee operational stability and continuous improvement.
Assumptions
- Standard release opportunities occur on a 6 week interval.
- Emergency releases may be scheduled as needed to accommodate critical security updates with known exploits
Releases
February 2025 Release
Release Schedule
To ensure a smooth transition and thorough testing, we are implementing the following release schedules for each platform:
Agency Platform I & II
Agency Platform II Distribution - 2.0.7.8 (Drupal 9)
Agency Platform Distribution - 7.103-M1 (Drupal 7)
- Development Environment (DEV): Monday, February 10th, 2025 by 3PM
- Test Environment (TEST): Monday, February 17th, 2025 by 3PM
- Live Environment (LIVE): Thursday, February 27th, 2025 after 5PM
Agency Platform 2.0.1.x-2
Release Schedule
Schedule:
- DEV - May 31, 2022 9:00 AM
- TEST - June 1, 2022 12:00 PM
- LIVE - June 2, 2022 5:00 PM
Agency Platform Releases August 2022 (Drupal 7 and Drupal 9)
Release Schedule
Schedule:
- DEV - August 2nd, 3021 at 9:00 AM
- TEST - August 3rd, 2021 at 12:00 PM
- LIVE - August 4th 2021 ar 5:00 PM
Agency Platform II (Drupal 9) Updates - March 2023
Release Schedule
Schedule:
- DEV - March 28th, 2023 9:00 AM
- TEST - March 29th, 2023 12:00 PM
- LIVE - March 30th, 2023 5:00 PM
Agency Platform Maintenance - April 2023
Release Schedule
Schedule:
- DEV environment - 4/25/23 approximately 9 A.M.
- TEST environments - 4/26/23 approximately 12 P.M.
- LIVE environments - 4/27/23 after 5 P.M.
Agency Platform II (Drupal 9) Patching and Maintenance - May 2023
Release Schedule
Schedule:
- DEV environment - 5/23/23 approximately 9 A.M.
- TEST environments - 5/24/23 approximately 12 P.M.
- LIVE environments - 5/25/23 after 5 P.M.
Agency Platform Drupal 9 Release - July 2023
Release Schedule
Schedule:
- DEV - June 30th, 2023 09:00 AM
- TEST - July 5th, 2023 07:00 AM
- LIVE - July 6th, 2023 5:00 PM
Agency Platform II Release - February 2024
Release Schedule
Schedule:
- DEV environment - 01/30/24 approximately 9 A.M.
- TEST environments - 01/30/24 approximately 12 P.M.
- LIVE environments - 02/08/24 after 5 P.M.